DoD TRIPWIRE METRICS
Cost Efficiency CPI = BCWP / ACWP Favorable is > 1.0, Unfavorable is < 1.0
Schedule Efficiency SPI = BCWP / BCWS Favorable is > 1.0, Unfavorable is < 1.0
VARIANCES Favorable is Positive, Unfavorable is Negative
Cost Variance CV = BCWP ACWP CV % = (CV / BCWP)
*
100
Schedule Variance SV = BCWP BCWS SV % = (SV / BCWS)
*
100
Variance at Completion VAC = BAC EAC
OVERALL STATUS
% Schedule = (BCWS
CUM
/ BAC)
*
100
% Complete = (BCWP
CUM
/ BAC)
*
100
% Spent = (ACWP
CUM
/ BAC)
*
100
BASELINE EXECUTION INDEX (BEI) = A Schedule Metric
BEI = Tasks with Actual Finish Date / (# of Baseline Tasks Scheduled to Finish Prior to Status Date
+Tasks Missing Baseline Start or Finish Date)
CRITICAL PATH LENGTH INDEX (CPLI) = A Schedule Metric
CPLI = (CP Length
(Time Now To Contract End)
) + Total Float
(To Contract End Baseline Finish)
) / CP Length
# ESTIMATE AT COMPLETION (EAC) = Actuals to Date + [(Remaining Work)/(Performance Factor)]
EAC
CPI
= ACWP
CUM
+ [(BAC BCWP
CUM
) / CPI
CUM
]
= BAC / CPI
CUM
EAC
Composite
= ACWP
CUM
+ [(BAC BCWP
CUM
) / (CPI
CUM *
SPI
CUM
)]
# § TO COMPLETE PERFORMANCE INDEX (TCPI)
TCPI
EAC
= Work Remaining / Cost Remaining = (BAC BCWP
CUM
) / (EAC ACWP
CUM
)
#
To Determine a Contract Level TCPI or EAC; You May Replace BAC with TAB
§ To Determine the TCPI
BAC or LRE
Replace EAC with BAC or LRE
EARNED VALUE MANAGEMENT
‘GOLD CARD
Management Reserve
Cost
Variance
Schedule Variance
ACWP
BCWP
BCWS
$
EAC
Time
Now
Completion
Date
PMB
TAB
BAC
Time
Hit / Miss = Month’s Tasks Completed ON or AHEAD / Month’s Tasks Scheduled to Complete
TW
TW
TW
TW
DoD TRIPWIRE METRICS
Cost Efficiency CPI = BCWP / ACWP Favorable is > 1.0, Unfavorable is < 1.0
Schedule Efficiency SPI = BCWP / BCWS Favorable is > 1.0, Unfavorable is < 1.0
VARIANCES Favorable is Positive, Unfavorable is Negative
Cost Variance CV = BCWP ACWP CV % = (CV / BCWP)
*
100
Schedule Variance SV = BCWP BCWS SV % = (SV / BCWS)
*
100
Variance at Completion VAC = BAC EAC
OVERALL STATUS
% Schedule = (BCWS
CUM
/ BAC)
*
100
% Complete = (BCWP
CUM
/ BAC)
*
100
% Spent = (ACWP
CUM
/ BAC)
*
100
BASELINE EXECUTION INDEX (BEI) = A Schedule Metric
BEI = Tasks with Actual Finish Date / (# of Baseline Tasks Scheduled to Finish Prior to Status Date
+Tasks Missing Baseline Start or Finish Date)
CRITICAL PATH LENGTH INDEX (CPLI) = A Schedule Metric
CPLI = (CP Length
(Time Now To Contract End)
) + Total Float
(To Contract End Baseline Finish)
) / CP Length
# ESTIMATE AT COMPLETION (EAC) = Actuals to Date + [(Remaining Work)/(Performance Factor)]
EAC
CPI
= ACWP
CUM
+ [(BAC BCWP
CUM
) / CPI
CUM
]
= BAC / CPI
CUM
EAC
Composite
= ACWP
CUM
+ [(BAC BCWP
CUM
) / (CPI
CUM *
SPI
CUM
)]
# § TO COMPLETE PERFORMANCE INDEX (TCPI)
TCPI
EAC
= Work Remaining / Cost Remaining = (BAC BCWP
CUM
) / (EAC ACWP
CUM
)
#
To Determine a Contract Level TCPI or EAC; You May Replace BAC with TAB
§ To Determine the TCPI
BAC or LRE
Replace EAC with BAC or LRE
EARNED VALUE MANAGEMENT
‘GOLD CARD
Management Reserve
Cost
Variance
Schedule Variance
ACWP
BCWP
BCWS
$
EAC
Time
Now
Completion
Date
PMB
TAB
BAC
Time
Hit / Miss = Month’s Tasks Completed ON or AHEAD / Month’s Tasks Scheduled to Complete
TW
TW
TW
TW
Downloaded from http://www.everyspec.com
资源描述:

当前文档最多预览五页,下载文档查看全文

此文档下载收益归作者所有

当前文档最多预览五页,下载文档查看全文
温馨提示:
1. 部分包含数学公式或PPT动画的文件,查看预览时可能会显示错乱或异常,文件下载后无此问题,请放心下载。
2. 本文档由用户上传,版权归属用户,天天文库负责整理代发布。如果您对本文档版权有争议请及时联系客服。
3. 下载前请仔细阅读文档内容,确认文档内容符合您的需求后进行下载,若出现内容与标题不符可向本站投诉处理。
4. 下载文档时可能由于网络波动等原因无法下载或下载错误,付费完成后未能成功下载的用户请联系客服处理。
关闭