DATA ITEM DESCRIPTION
Title: Cost Breakdown Structure Summary Report
Number: DI-FNCL-80165A Approval Date: 30 OCT 2006
AMSC Number: 7620 Limitation: N/A
DTIC Applicable: N/A GIDEP Applicable: No
Office of Primary Responsibility: NS/DA01
Applicable Forms: DD Form 2417
Use/relationship:
The Cost Breakdown Structure (CBS) Summary Report provides the project cost
allocation by cost category and applicable fiscal appropriate determined by the contractor
to deliver and support a system during the performance of a contract.
This Data Item Description (DID) contains the format and content preparation
instructions for each tech data product generated by the specific and discrete task
requirement as delineated in the contract.
This DID is applicable to all cost reimbursable type contracts over $100,000 in value and
6 months duration, involving development of hardware or software.
It is not intended that all the requirements contained herein shall be applied to every
program or program phase. Portions of this DID are subject to deletion tailoring
depending upon the program phases in which it is applied in the contract.
This DID is related to DI-FNCL-80166B, Cost Breakdown Structure Detailed Report.
This DID supersede DI-FNCL-80165.
Requirements:
1. Reference documents: The applicable issue of the documents cited herein, including
their approval dates and dates of any applicable amendments, notices, and revisions,
shall be as cited in the current issue of the DODISS at the time of the solicitation; for
non DODISS-listed documents, as stated herein.
2. Format: The Cost Breakdown Structure Summary Report shall be prepared using the
DD Form 2417, See Figure 1.
3. Content:
3.1 Header.
3.1.1 System/Project Identification. Identification of the system or project.