USACE / NAVFAC / AFCEC / NASA UFGS-02 54 19.16 (February 2021)
------------------------------------
Preparing Activity: USACE Superseding without Revision
UFGS-
02 54 21 (October 2010)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 54 19.16
BIOREMEDIATION OF SOILS USING WINDROW COMPOSTING
02/21
PART 1 GENERAL
1.1 MEASUREMENT AND PAYMENT
1.1.1 Bench-Scale Testing
1.1.2 Field Demonstration
1.1.3 Contaminated Soils Treatment Unit Price
1.1.4 Oversize Materials from Contaminated Areas
1.2 REFERENCES
1.3 PROCESS DESCRIPTION
1.4 DESIGN REQUIREMENTS
1.4.1 Composting Treatment Pad
1.4.1.1 Treatment Pad Sizing
1.4.1.2 Other Work Area Surfaces
1.4.2 Contact Water Management System and Design Storm
1.4.2.1 Perimeter Berms
1.4.2.2 Storage Volume
1.4.2.3 Reuse, Treatment, and Disposal
1.4.2.4 Irrigation Equipment
1.4.3 Weather Cover
1.4.4 Stockpiles
1.4.5 Amendment Storage Facilities
1.4.5.1 Paved Storage Area
1.4.5.2 Unpaved Storage Area
1.4.6 Accuracy of Measurement Equipment
1.5 PERFORMANCE REQUIREMENTS
1.5.1 Treatment Criteria and Criteria for Reuse of Composted Soil
1.5.1.1 Treatment Criteria for Composted Soil
1.5.1.2 Criteria for Reuse of Composted Soil
1.5.2 Treatment Criteria for Contact Water
1.5.3 Treatment Criteria for Other Waste
1.6 COMPOSTING WORK PLAN
1.6.1 Schedule
1.6.2 Project Organization and Personnel
1.6.3 Selection of Amendments
SECTION 02 54 19.16 Page 1