USACE / NAVFAC / AFCEC / NASA UFGS-32 13 14.13 (November 2022)
------------------------------------
Preparing Activity: USACE UFGS-32 13 14.13 (August 2019)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 32 - EXTERIOR IMPROVEMENTS
SECTION 32 13 14.13
CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY DUTY PAVEMENTS
11/22
PART 1 GENERAL
1.1 UNIT PRICES
1.1.1 Measurements
1.1.2 Payments
1.1.2.1 Unit Price
1.1.2.2 Lump Sum
1.1.3 Payment of Lots
1.1.4 Payment Adjustment for Smoothness
1.1.4.1 Straightedge Testing
1.1.4.2 Profilograph Testing
1.1.4.3 Aircraft Arresting Systems
1.1.5 Payment Adjustment for Plan Grade
1.1.6 Payment Adjustment for Thickness
1.2 REFERENCES
1.3 SUBMITTALS
1.4 QUALITY CONTROL
1.4.1 Contractor Quality Control (CQC) Staff
1.4.2 Other Staff
1.4.3 Laboratory Accreditation and Validation
1.4.3.1 Aggregate Testing and Mix Proportioning
1.4.3.2 Acceptance Testing
1.4.3.3 Contractor Pavement Quality Control Plan
1.4.3.4 Laboratory Inspection
1.4.4 Preconstruction Testing of Materials
1.4.4.1 Aggregates
1.4.4.2 Chemical Admixtures, Curing Compounds and Epoxies
1.4.4.3 Testing of Cementitious Materials
1.4.5 Testing During Construction
1.4.6 Test Section
1.4.6.1 General
1.4.6.2 Pilot Lane
1.4.6.3 Fill-In Lane
1.4.6.4 Testing and Inspection
SECTION 32 13 14.13 Page 1