DATA ITEM DESCRIPTION
Title: SYSTEM SAFETY PROGRAM PROGRESS REPORT (SSPPR)
Preparing Activity: 40 (AFMC/SE)
Project Number: SAFT-2015-007
Use/Relationship: The System Safety Program Progress Report (SSPPR) is used to cover
periodic reviews of safety activities and to monitor pro
gress of contractor system safety
efforts.
a. This Data Item Description (DID) contains the content and format preparation instructions
for the data product generated by the specific and discrete task requirement as delineated in
the contract.
b. This DID is related to DI-SAFT-80101, System Safety Hazard Analysis Report (SSHAR);
DI-SAFT-80102, Safety Assessment Report (SAR); and DI-SAFT-80106, Health Hazard
Assessment Report (HHAR).
c. Do not use DI-ADMN-81250, Conference Minutes, in conjunction with this DID.
(Copies of these DIDs are available online at http://quicksearch.dla.mil
.)
d. This DID supersedes DI-SAFT-80105B.
Requirements:
1. Reference documents. The applicable issue of the documents cited herein, including their
approval dates and dates of any applicable amendments, notices, and revisions, shall be as
specified in the contract.
2. Format. The SSPPR shall be in the contractor’s format.
3. Content. The SSPPR shall include a description of the general progress made relative to
the system safety program during the reporting period and the projected work for the next
reporting period. The report shall contain the following information in narrative form:
a. A brief summary of activities, progress, and status of the safety effort. It shall highlight
significant achievements and problems. It shall include progress toward completion of safety
data items prepared or in work.
b. Newly recognized significant hazards and significant changes in the degree of control on
known hazards
c.
Inventory of identified hazards, with each hazard tabulated by sequence number,
identified by the initial risk index value and revised risk index value after incorporation of
hazard mitigation, action taken to date, and its action status: ope
Include any hazards which the contractor believes cannot be reduced to an acceptable level
of risk and will require managing activity action.