USACE / NAVFAC / AFCEC / NASA UFGS-33 01 30.72 (November 2021)
------------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-33 01 30.7
2 (May 2016)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 33 - UTILITIES
SECTION 33 01 30.72
RELINING SEWERS
11/21
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.3 ADMINISTRATIVE REQUIREMENTS
1.3.1 Scheduling
1.4 SUBMITTALS
1.5 QUALITY CONTROL
1.5.1 Qualifications
1.5.1.1 Contractor's Qualifications
1.5.1.2 CIPP Installer's Qualifications
1.5.1.3 Superintendent's Qualifications
1.5.1.4 Quality Control Specialist
1.5.1.5 Liner Manufacturer
1.5.1.6 Quality Control Laboratory
1.5.2 Quality Control Plan
1.6 DELIVERY, STORAGE, AND HANDLING
1.6.1 Resin
1.7 PROJECT/SITE CONDITIONS
1.7.1 Environmental Requirements
1.7.1.1 Disposal Of Process Water
1.8 WARRANTY
1.8.1 Warranty-TV Inspection
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
2.1.1 Design Requirements
2.1.1.1 Structural Requirements
2.1.1.1.1 Cured-In-Place Pipe
2.1.1.1.2 Fold and Form Pipe
2.1.2 Performance Requirements
2.1.2.1 Cured-In-Place Pipe
2.1.2.2 Fold-And-Form Pipe
SECTION 33 01 30.72 Page 1