DEPARTMENT OF THE ARMY
U.S. Army Corps
of
Engineers
Washington, DC
20314-1000
ER
415-1-10
CECW-CE
Regulation
No. 415-1-10
30 April2012
Construction
CONTRACTOR SUBMITTAL PROCEDURES
TABLE-OF CONTENTS
Paragraph
Page
1.
2.
3.
Purpose.....................................................................................
1
Applicability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Distribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
4.
References
................................................................................
.
5.
General
....................................................................................
.
6.
Policy
............
·
..........................................................................
..
7.
Submittal Classifications for Design-Bid-Build Method
of
Delivery
............
.
8.
Submittal Classifications for Design-Build Method
of
Delivery
.................
..
9.
Government Pre-Award Responsibilities
...............................................
.
10.
Contractor Post-Award Responsibilities
..............................................
.
11.
Government Post-Award Responsibilities
............................................
.
12.
Implementation
of
Management Procedures
.........................................
.
13.
Disposition
of
Gove:inrnent Submittal Files After Contract Completion
........
.
I
APPENDIXES
1
1
2
2
4
7
8
11
14
14
Appendix A - Submittal Register (ENG Form
4288)........
....
........
....
......
...
A-1
Appendix B - Transmittal Cover Sheet (ENG Form 4025) ..
....
..
....
..
....
....
..... B-1
Appendix C - Submittal Type and Action Code Definitions . . . . . . . . . . . . . . . . . . . . . . . . .
C-1
Appendix D - Transmittal Routing Slip (ENG Form 4026) ... ... .. . .. . ... . ... .. . ....
D-1
1