USACE / NAVFAC / AFCEC / NASA UFGS-01 35 13 (November 2020)
Change 1 - 02/22
------------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-01 35 13 (
November 2011)
UFGS-01 35 13.05 20 (November 2007)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 13
SPECIAL PROJECT PROCEDURES
11/20, CHG 1: 02/22
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 Landing Areas
1.2.2 Safety Precaution Areas
1.2.3 Federal Aviation Administration (FAA) Notice of Proposed
Construction or Alteration
1.3 SUBMITTALS
PART 2 PRODUCTS
2.1 AIRFIELD OBSTRUCTION LIGHTS
PART 3 EXECUTION
3.1 HAZARDS TO [AIRFIELD][HELIPORT] OPERATION
3.1.1 Work in Proximity to [Landing Areas] [Landing Strips] [Landing
Pad(s)]
3.1.2 Contractor FAA Notification
3.1.3 Schedule of Work/Aircraft Operating Schedules
3.1.3.1 Construction Operations Plan
3.1.3.2 Existing Conditions Survey
3.1.4 Daytime Markings
3.1.5 Nighttime Markings
3.1.6 Excavation
3.1.7 Contractor Safety Precautions
3.1.8 Base Civil Engineering (BCE) Work Clearance Request
3.1.9 Radio Contact
3.2 HARBOR WATERWAYS
3.2.1 Hazards to Navigation
3.2.2 Submarine Cables or Underwater Utilities
3.2.3 RIMPAC Operational Exercises
SECTION 01 35 13 Page 1