USACE / NAVFAC / AFCEC / NASA UFGS-02 54 19.13 (February 2021)
------------------------------------
Preparing Activity: USACE Superseding without Revision
UFGS-
02 54 20 (February 2010)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 54 19.13
BIOREMEDIATION USING LANDFARMING
02/21
PART 1 GENERAL
1.1 MEASUREMENT AND PAYMENT
1.1.1 Bench-Scale Testing
1.1.2 Field Demonstration
1.1.3 Contaminated Soils Treatment Unit Price
1.1.4 Oversize Materials from Contaminated Areas
1.2 REFERENCES
1.3 PROCESS DESCRIPTION
1.4 DESIGN REQUIREMENTS
1.4.1 Landfarming Treatment Cell
1.4.1.1 Treatment Cell Sizing
1.4.1.2 Porous Drainage Layer
1.4.1.3 Leachate Controls and Collection
1.4.1.4 Geomembrane and Clay Liners
1.4.2 Contact Water Management System and Design Storm
1.4.2.1 Perimeter Berms
1.4.2.2 Storage Volume
1.4.2.3 Reuse, Treatment, and Disposal
1.4.3 Irrigation Equipment
1.4.4 Weather Cover
1.4.5 Stockpiles
1.4.6 Other Work Area Surfaces
1.4.7 Accuracy of Measurement Equipment
1.5 PERFORMANCE REQUIREMENTS
1.5.1 Treatment Criteria and Criteria for Reuse of Treated Soil
1.5.1.1 Treatment Criteria for Soil
1.5.1.2 Criteria for Reuse of Treated Soil
1.5.1.3 Particle Size Criteria for Treated Soil
1.5.2 Treatment Criteria for Contact Water
1.5.3 Treatment Criteria for Other Waste
1.6 LANDFARMING WORK PLAN
1.6.1 Schedule
1.6.2 Project Organization and Personnel
SECTION 02 54 19.13 Page 1