USACE / NAVFAC / AFCEC / NASA UFGS-41 22 13.15 (November 2022)
------------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-41 22 13.1
5 (February 2020)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
SECTION 41 22 13.15
BRIDGE CRANES, OVERHEAD ELECTRIC, UNDER RUNNING TROLLEY
11/22
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.3 SYSTEM DESCRIPTION
1.3.1 Crane Design Criteria
1.3.1.1 General
1.3.1.2 Classification
1.3.1.3 Rated Speeds
1.4 VERIFICATION OF DIMENSIONS
1.5 SUBMITTALS
1.6 QUALITY ASSURANCE
1.6.1 Manufacturer Qualification
1.6.2 Pre-Delivery Inspections
1.6.2.1 Hook Proof Test
1.6.2.2 Inspection of Hook Assembly
1.6.2.2.1 Hook Non-Destructive Test (NDT)
1.6.2.3 Insulated Link Non-Destructive Test (NDT)
1.6.3 Drawings: Overhead Electric Crane System
1.6.4 Design Data: Load and Sizing Calculations
1.6.5 Certificates
1.6.6 Welding Qualifications and Procedure
1.7 CRANE SAFETY
1.7.1 Nuclear Safety Analysis
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 General
2.1.2 Nameplates
2.1.3 Capacity Marking
2.1.4 Safety Warnings
2.2 STRUCTURAL REQUIREMENTS
2.2.1 Structural Connections
SECTION 41 22 13.15 Page 1