Title: HEMP PROTECTION SUBSYSTEM PERFORMANCE TEST PLAN
Number: DI-EMCS-82013 Approval Date: 20160404
AMSC Number: 9607 Limitation: N/A
DTIC Applicable: Yes GIDEP Applicable: N/A
http://www.dtic.mil/dtic/submit/
Office of Primary Responsibility: DTRA-DS
Applicable Forms: None
Use/Relationship:
The HEMP Protection Subsystem (HPS) Performance Testing Plan describes the methods of test
analysis and inspection used by the contractor to verify compliance with the HEMP interface and
performance requirements of a ship during the engineering development phase. The Plan
provides the means for the government to understand and duplicate verification methods used by
the contractor to verify HEMP protection requirements.
1. This DID contains the format, content, and intended use information for the data product
resulting from the work tasks described in Appendix B and Appendix C of MIL-STD-4023 and
is intended for ship systems. It is normally applied to the System Design and Development
phase of a program, but it can be used in any phase.
2. This DID is related to DI-EMCS-82014 and DI-EMCS-82012.
Requirements:
1. Reference documents. The applicable issuance of the documents cited herein, including their
approval dates and any applicable amendments, notices, or revisions shall be as cited in the
ASSIST Online at the time of the solicitation, or for non-ASSIST listed documents, as stated
herein. HEMP Protection Subsystem Performance Test Plan classification shall be determined
using DTRA Security Classification Guide for DoD Electromagnetic Pulse (EMP) Programs and
Activities (U) available by mail request to ATTN: J9/NT-NTSA/Rooney M., Defense Threat
Reduction Agency, 8725 John J. Kingman Road, MSC 6201 Fort Belvoir, Virginia 22060-6201
and any relevant system specific classification guides.
2. Format. The Plan shall be in contractor format.
3. Content. The Plan shall describe the test plan for Electromagnetic Barrier Point-of-Entry
testing for each requirement specified in the contract for the ship being developed (see MIL-
STD-4023 section 5 and Appendix C).
3.1 Summary information. The Plan shall summarize the following:
3.1.1 Introduction.
Downloaded from http://www.everyspec.com
资源描述:

当前文档最多预览五页,下载文档查看全文

此文档下载收益归作者所有

当前文档最多预览五页,下载文档查看全文
温馨提示:
1. 部分包含数学公式或PPT动画的文件,查看预览时可能会显示错乱或异常,文件下载后无此问题,请放心下载。
2. 本文档由用户上传,版权归属用户,天天文库负责整理代发布。如果您对本文档版权有争议请及时联系客服。
3. 下载前请仔细阅读文档内容,确认文档内容符合您的需求后进行下载,若出现内容与标题不符可向本站投诉处理。
4. 下载文档时可能由于网络波动等原因无法下载或下载错误,付费完成后未能成功下载的用户请联系客服处理。
关闭