USACE / NAVFAC / AFCEC / NASA UFGS-02 62 13.00 10 (August 2018)
------------------------------------
Preparing Activity: USACE Superseding
UFGS-11 24 27 (
October 2007)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 02 - EXISTING CONDITIONS
SECTION 02 62 13.00 10
AIR AND STEAM STRIPPING
08/18
PART 1 GENERAL
1.1 UNIT PRICES
1.2 REFERENCES
1.3 ADMINISTRATIVE REQUIREMENTS
1.3.1 [Pre-Installation Meetings] [Partnering Conference]
1.4 SUBMITTALS
1.5 QUALITY CONTROL
1.5.1 Qualifications
1.5.1.1 Constructor
1.5.1.2 Manufacturer's Representative
1.5.1.3 Welding
1.5.2 Single Source Supplier
1.6 DELIVERY, STORAGE, AND HANDLING
PART 2 PRODUCTS
2.1 SYSTEM DESCRIPTION
2.1.1 Design Requirements
2.1.2 Influent Inorganic Chemical Conditions
2.1.3 System Performance Requirements
2.1.3.1 Air to Water Ratio
2.1.3.2 Influent and Effluent Organic Contaminant Concentrations
2.1.3.3 Operating Schedule
2.1.4 Seismic Protection
2.1.5 Design Loads
2.1.6 Foundations
2.1.7 Anchors
2.1.7.1 Number of Anchors
2.1.7.2 Anchor Bolts and Straps
2.1.7.3 Attachment
2.1.7.4 Seismic Requirements
2.2 EQUIPMENT
2.2.1 Standard Products
SECTION 02 62 13.00 10 Page 1