USACE / NAVFAC / AFCEC / NASA UFGS-07 27 10.00 10 (August 2019)
Change 1 - 02/20
------------------------------------
Preparing Activity: USACE Superseding
UFGS-07 27 10.0
0 10 (May 2014)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
SECTION 07 27 10.00 10
BUILDING AIR BARRIER SYSTEM
08/19, CHG 1: 02/20
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 DEFINITIONS
1.3.1 Air Barrier Accessory
1.3.2 Air Barrier Assembly
1.3.3 Air Barrier Component
1.3.4 Air Barrier Envelope
1.3.5 Air Barrier Material
1.3.6 Air Barrier System
1.3.7 Air Leakage Rate
1.3.8 Air Leakage
1.3.9 Air Permeance
1.3.10 Environmental Separator
1.3.11 Vapor Permeance
1.4 PREPARATORY PHASE OR PRECONSTRUCTION CONFERENCE
1.5 SUBMITTALS
1.6 AIR BARRIER ENVELOPE SURFACE AREA AND LEAKAGE REQUIREMENTS
1.7 AIR BARRIER INSPECTOR
1.8 DESIGN REVIEW
PART 2 PRODUCTS
2.1 AIR BARRIER
PART 3 EXECUTION
3.1 QUALITY CONTROL
3.1.1 Documentation and Reporting
3.1.2 Construction Mock-Up
3.1.3 Quality Control Testing And Inspection
3.2 REPAIR AND PROTECTION
SECTION 07 27 10.00 10 Page 1