USACE / NAVFAC / AFCEC / NASA UFGS-07 27 36 (May 2017)
Change 2 - 08/20
------------------------------------
Preparing Activity: NAVFAC
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
SECTION 07 27 36
SPRAY FOAM AIR BARRIERS
05/17, CHG 2: 08/20
PART 1 GENERAL
1.1 REFERENCES
1.2 RELATED REQUIREMENTS
1.3 DEFINITIONS
1.3.1 Long Term Thermal Resistance (LTTR)
1.3.2 SPFA TechDocs
1.4 SUBMITTALS
1.5 MISCELLANEOUS REQUIREMENTS
1.5.1 Shop Drawings
1.5.2 Product Data
1.5.3 Mockup
1.5.4 Test Reports
1.6 DELIVERY, STORAGE, AND HANDLING
1.6.1 Delivery
1.6.2 Storage
1.6.3 Handling
1.6.3.1 Venting and Handling of Material Containers
1.7 FIELD PEEL ADHESION TEST
1.8 AIR BARRIER TESTING
1.9 SAFETY PROVISIONS
1.9.1 Fire Prevention
1.9.1.1 Fire Extinguishers
1.9.2 Respirator Plan
1.9.3 Isolation
1.9.4 Respirators and Eye Protection
1.9.5 Clothing and Gloves
1.9.6 Additional Requirements
1.10 QUALITY ASSURANCE
1.10.1 Qualification of Manufacturer
1.10.2 Qualification of Installer
1.10.3 General Quality Requirements
1.11 PRECONSTRUCTION MEETING
1.12 ENVIRONMENTAL CONDITIONS
SECTION 07 27 36 Page 1