USACE / NAVFAC / AFCEC / NASA UFGS-07 84 00 (May 2010)
Change 1 - 08/13
------------------------------------
Preparing Activity: USACE Superseding
UFGS-07 84 00 (
October 2007)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
SECTION 07 84 00
FIRESTOPPING
05/10, CHG 1: 08/13
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 SEQUENCING
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
1.5.1 Installer
1.5.2 Inspector Qualifications
1.6 DELIVERY, STORAGE, AND HANDLING
PART 2 PRODUCTS
2.1 FIRESTOPPING SYSTEM
2.2 FIRESTOPPING MATERIALS
2.2.1 Fire Hazard Classification
2.2.2 Toxicity
2.2.3 Fire Resistance Rating
2.2.3.1 Through-Penetrations
2.2.3.1.1 Penetrations of Fire Resistance Rated Walls and
Partitions
2.2.3.1.2 Penetrations of Fire Resistance Rated Floors,
Floor-Ceiling Assemblies and the Ceiling Membrane of Roof-Ceiling
Assemblies
2.2.3.1.3 Penetrations of Fire and Smoke Resistance Rated Walls,
Floors, Floor-Ceiling Assemblies, and the ceiling membrane of
Roof-Ceiling Assemblies
2.2.3.2 Construction Joints and Gaps
2.2.4 Material Certification
PART 3 EXECUTION
3.1 PREPARATION
3.2 INSTALLATION
SECTION 07 84 00 Page 1