USACE / NAVFAC / AFCEC / NASA UFGS-31 00 00 (August 2008)
Change 2 - 02/21
------------------------------------
Preparing Activity: USACE Superseding
UFGS-31 00 00 (
July 2006)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 31 - EARTHWORK
SECTION 31 00 00
EARTHWORK
08/08, CHG 2: 02/21
PART 1 GENERAL
1.1 MEASUREMENT PROCEDURES
1.1.1 Excavation
1.1.2 Piping Trench Excavation
1.1.3 Rock Excavation for Trenches
1.1.4 Topsoil Requirements
1.1.5 Overhaul Requirements
1.1.6 Select Granular Material
1.2 PAYMENT PROCEDURES
1.2.1 Classified Excavation
1.2.2 Piping Trench Excavation
1.2.3 Rock Excavation for Trenches
1.2.4 Unclassified Excavation
1.2.5 Classified Borrow
1.2.6 Unclassified Borrow
1.2.7 Authorized Overhaul
1.2.8 Sheeting and Bracing
1.2.8.1 Timber Sheeting
1.2.8.2 Steel Sheeting and Soldier Piles
1.3 CRITERIA FOR BIDDING
1.4 REFERENCES
1.5 DEFINITIONS
1.5.1 Satisfactory Materials
1.5.2 Unsatisfactory Materials
1.5.3 Cohesionless and Cohesive Materials
1.5.4 Degree of Compaction
1.5.5 Overhaul
1.5.6 Topsoil
1.5.7 Hard/Unyielding Materials
1.5.8 Rock
1.5.9 Unstable Material
1.5.10 Select Granular Material
1.5.10.1 General Requirements
SECTION 31 00 00 Page 1