PART V - MPT MILESTONES
COG CODE MPT MILESTONES DATE STATUS
PDA Awarded Production Contract Sep 86 Complete
PDA Began Analysis of MPT Requirements Dec 86 Complete
PDA Distributed Draft NTP for Review May 87 Complete
ACNO Programmed Manpower and Training Resource Requirements Jun 87 Complete
ACNO/DMSO Chaired NTP Conference Jun 87 Complete
PDA Submitted Proposed NTP to CNO for Approval Aug 87 Complete
ACNO (MPT) Approved NTP Sep 87 Complete
TSA Began Initial Training Mar 89 Complete
TSA Began Training Services Mar 89 Complete
TSA Delivered Curricula Materials Mar 89 Complete
PDA Began Fleet Introduction Jun 89 Complete
TA Began Follow-On Training Sep 89 Complete
DCNO Initiated OPNAV Form 1000/4A Oct 89 Complete
DCNO (MPT) Promulgated Updated NTP Oct 89 Complete
DCNO (MPT) Promulgated Activity Manpower Authorizations Nov 91 Complete
OPTEVFOR Began Follow-On Test And Evaluation Jul 92 Complete
ACNO (MPT) Promulgated Updated NTP Oct 92 Complete
ACNO (MPT) Promulgated Updated NTP Dec 93 Complete
DA Distribute Updated Draft NTSP for Review Nov 02 Pending
DA Forward Proposed NTSP to CNO for approval Mar 03 Pending
OPO Approve Updated NTSP Apr 03 Pending