USACE / NAVFAC / AFCEC / NASA UFGS-26 27 14.00 20 (February 2021)
Change 1 - 05/21
------------------------------------
Preparing Activity: NAVFAC Superseding
UFGS-26 27 14.0
0 20 (February 2011)
UNIFIED FACILITIES GUIDE SPECIFICATIONS
References are in agreement with UMRL dated October 2022
**************************************************************************
SECTION TABLE OF CONTENTS
DIVISION 26 - ELECTRICAL
SECTION 26 27 14.00 20
ELECTRICITY METERING
02/21, CHG 1: 05/21
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 QUALITY ASSURANCE
1.3.1 Installation Drawings
1.3.2 Standard Products
1.3.3 Material and Equipment Manufacturing Data
1.4 MAINTENANCE
1.4.1 Additions to Operation and Maintenance Data
1.5 WARRANTY
1.6 SYSTEM DESCRIPTION
1.6.1 System Requirements
1.6.2 Selection Criteria
PART 2 PRODUCTS
2.1 ELECTRICITY METERS AND ACCESSORIES
2.1.1 Physical and Common Requirements
2.1.2 Potential Transformer Requirements
2.1.3 Current Transformer Requirements
2.1.4 Meter Requirements
2.1.5 Disconnect Method
2.1.6 Installation Methods
2.2 COMMUNICATIONS INTERFACES
2.3 SPARE PARTS
2.4 METERING SYSTEM SCHEDULE
PART 3 EXECUTION
3.1 INSTALLATION
3.1.1 Existing Condition Survey
3.1.1.1 Existing Meter Sockets
3.1.1.2 Existing Installations
SECTION 26 27 14.00 20 Page 1