DATA ITEM DESCRIPTION
Title: Reliability Test Plan
Number: DI-NDTI-81585 Approval Date: 5 October 2000
AMSC Number: G7400 Limitation: N/A
DTIC Applicable: No GIDEP Applicable: No
Office of Primary Responsibility: G/Y243
Applicable Forms: N/A
Use/relationship:
This plan describes the overall reliability test planning and its total
integrated test requirements. It delineates required reliability tests,
their purpose and schedule. This document will be used by the procuring
activity for review, approval, and subsequent surveillance and
evaluation of the contractor's reliability test program.
Requirements:
1. Reference documents: None
2. Format: Contractor format is authorized.
3. Content: The Reliability Test Plan shall identify and describe
planned contractor activities for implementation of reliability test and
Environmental Stress Screening (ESS), if required, by the contract. The
plan shall contain a complete listing of all tests to be conducted for
the primary purpose of obtaining data for use in reliability analysis
and evaluation of the contract item or any constituent elements thereof.
The test plan shall include the following:
a. Test objectives and requirements of each reliability test.
b. Test item configuration description and quantity to be tested.
c. Test conditions, environmental, operational and performance
profiles, and the duty cycle.
d. Test schedules and milestones including the test program review
schedule.
e. Test conduct ground rules, failure and accept criteria, and
interface boundaries.
f. Test facility and equipment descriptions and requirements,
including provisions for voltage, temperature, and vibration.
g. Government furnished property requirements and impact.
h. List of test reports to be issued.
i. Failure recurrence control system to be used to ensure
corrective action.
j. List of test procedures to be used.
k. Definition of items termed replaceable at failure.
l. Detailed reason for each proposed deviation.
m. Assignment of specific responsibilities.
n. Access control to test area and equipment under test.
o. Specific contractor/procuring activity organizational
element
with respective authorities and responsibilities for implementation
of reliability testing as a mutually agreed to and approved by the
procuring activity.
Page 1 of 2 Pages
Downloaded from http://www.everyspec.com
资源描述:

当前文档最多预览五页,下载文档查看全文

此文档下载收益归作者所有

当前文档最多预览五页,下载文档查看全文
温馨提示:
1. 部分包含数学公式或PPT动画的文件,查看预览时可能会显示错乱或异常,文件下载后无此问题,请放心下载。
2. 本文档由用户上传,版权归属用户,天天文库负责整理代发布。如果您对本文档版权有争议请及时联系客服。
3. 下载前请仔细阅读文档内容,确认文档内容符合您的需求后进行下载,若出现内容与标题不符可向本站投诉处理。
4. 下载文档时可能由于网络波动等原因无法下载或下载错误,付费完成后未能成功下载的用户请联系客服处理。
关闭